Nissan to build the Kicks at Sunderland, with no extra jobs
Nissan will spend £170 million so the Kicks hybrid can be built in Sunderland. The plant employs about 6,000 people, is running at about half capacity, and the company said the plan creates no jobs. There is no start date.
The Industrial Brief · Editorial · 16 September 2026 · 4 min

Nissan will spend £170 million to build the second-generation Kicks at Sunderland. The car is a hybrid. It is already made in Japan, Mexico and Brazil. In Britain it would sit on the same site as the Qashqai, the Juke and the Leaf. The company said the plan does not create jobs and does not change the shift pattern. It is meant to help keep the jobs that are already there.
There is no date for the first car. The BBC reported that Nissan did not give one. A sum without a start of production is a model allocation, not a volume plan. Anyone pricing tooling into Wearside on the back of this announcement is pricing a derivative whose year is still blank.
- £170m
- Nissan’s figure for the Kicks at Sunderland
- 6,000
- People on the site, about
- Half
- Capacity the plant is running at, per the BBC
- None
- New jobs, and no change of shift
The hall is already half empty
Sunderland employs about 6,000 people and is running at about half capacity. Earlier this year Nissan merged two production lines on the site. A plant that has just taken a line out does not need a press release to explain what the next model is for. It needs something to put on the line that remains. The Kicks is that something, if it arrives, and at a scale Nissan has not stated.
The same week, the company was still in talks with Chery about building Chinese cars at Sunderland, to use more of the plant. Nissan confirmed the talks were continuing. A second manufacturer on the site is a different industrial fact from a tenth Nissan model. One fills a badge. The other fills hours. Neither has a date.
Earlier this year Nissan said it would cut 900 jobs in Europe, including part of a warehouse in Barcelona, and that cars for the Nordic countries would be imported rather than held there. Sunderland is being given a model in the middle of a European cut, not at the start of a hiring round. The safeguarding language is the point. The company did not describe a bigger plant. It described a reason not to make this one smaller.
What a supplier is actually being offered
The Kicks uses Nissan’s series-hybrid arrangement: a petrol engine makes electricity, and an electric motor drives the wheels. That is a powertrain derivative on a site that already builds hybrids and a battery car, not a new process from a clean floor. The £170 million will be absorbed by tools, tryout and the work of putting one more body through a hall that has already been simplified. It is not the budget of a second shift.
For a firm that sells into Sunderland, the useful split is this. A new model can move part numbers, coatings, and a hybrid transmission. It does not, on the company’s own account, move headcount or the shift pattern. A quote that assumes the plant goes from half capacity to full, because a minister called it confidence, is a quote for a factory Nissan has not described. The factory it described still has no start date, an open conversation with Chery, and about half of its hours unused.
Get the Monday briefing
The week in manufacturing, for people who specify and buy. Eight minutes, before the first meeting.
SubscribeFurther reading

News · Production
UK manufacturing output rose 1.2% in August as pharmaceutical production jumped 5.1%
Pharmaceuticals supplied more than half of the month's manufacturing growth. Also in this roundup: £40m for robotics adoption hubs, Schaeffler's job cuts running a year early, and new defence and chip-equipment capacity in Poland, Spain, Georgia and North Carolina.
The Industrial Brief · 17 Oct 2026 · 7 min

News · Production
Japan will put up to $21bn into two GlobalFoundries chip fabs in New York
The first 300mm fab at Malta is due online in 2029 on about $10bn of Japanese money. A second fab of similar size would need a further $10bn. The US Commerce Department also takes about 4% of GlobalFoundries.
The Industrial Brief · 16 Oct 2026 · 4 min

News · Production
Lockheed Martin puts $300m into its Texas missile parts plant
The Grand Prairie site that machines parts for PAC-3 MSE, THAAD and PrSM will grow past 735,000 sq ft, with a 24-machine Hadrian cell due to run inside the plant from early 2027 under a seven-year deal.
The Industrial Brief · 15 Oct 2026 · 4 min