For a heavy plant, the power connection now decides the site
For mills, furnaces, and gigafactories, megawatts have become as scarce as skilled operators. Location is now a power decision wearing a real-estate costume.
The Industrial Brief · Editorial · 9 September 2026 · 8 min

Ask a steel CFO what limits output and you will still hear scrap, electrodes, and orders. Ask again after a winter of industrial power prices and you will hear the grid. Electric-arc furnaces, aluminium smelters, semiconductor fabs, and battery dry rooms are now competing with data centers for interconnection. In more than a few regions, the queue is the strategy.
This is new in degree, not in kind. Heavy industry always followed energy. What is new is the simultaneity: AI campuses, EV plants, and reshoring projects all arriving at substations that were sized for a quieter decade. Small modular reactor startups raised nearly $4 billion in 2024. That is a tell. When manufacturers start talking like utilities, the constraint has moved.
Site selection is a megawatt model
Boards still approve plants on labour, logistics, and incentives. The plants that will actually run through 2030 are the ones that modelled firm power — including the 2 a.m. price — before they modelled the break-room. Behind-the-meter generation, long-term PPAs, and the unfashionable option of simply not building in a congested node are now operating decisions. So is demand response. A line that can shed load without scrapping a batch has a different P&L from one that cannot.
A gigafactory without a substation date is a rendering. Treat the interconnection agreement with the same gravity as the tool purchase order.
Emissions accounting is tightening at the same moment. TechInsights expects semiconductor fabrication emissions to approach 200 million metric tons of CO₂e this year, with Taiwan, South Korea, and China doing most of the growing. Complexity is the driver: more silicon, more packaging, more energy per good die. The manufacturers who will still have a licence to operate in Europe are the ones who can show the electron as well as the part.
- 200 Mt
- Projected 2026 semiconductor-fab CO₂e
- $3.9bn
- SMR startup funding in 2024
- 24/7
- The only power profile a fab can actually use
Get the Monday briefing
The week in manufacturing, for people who specify and buy. Eight minutes, before the first meeting.
SubscribeFurther reading

News · Energy
Sumitomo Electric opens the UK's first HVDC subsea cable factory at Nigg
The £350m plant at Nigg on the Cromarty Firth will make 525kV cable for National Grid's Sea Link and SSEN Transmission's Shetland 2. Sea Link's planning decision is due by 30 October, and Shetland 2 has not yet applied.
The Industrial Brief · 20 Oct 2026 · 4 min

Now · Energy
Microsoft pulls out of Nscale's planned data centre in Loughton, Essex
Microsoft was the only announced customer for Nscale's planned site, The Telegraph reported. Neither the paper nor Microsoft has said why it pulled out. Nscale says it is looking at other ways to power the site.
The Industrial Brief · 18 Oct 2026 · 2 min

News · Energy
Eligible manufacturers in Great Britain can cut electricity costs by up to 25% from April 2027 — applications close on 30 November
The British Industrial Competitiveness Scheme is now open. Relief comes as exemptions from three electricity policy levies, not a cash grant, and only for sites that clear the sector, product and usage tests.
The Industrial Brief · 12 Oct 2026 · 5 min